Baihetan Dam: Concrete pouring at #4 Section of auxiliary weir reaches dam crest
Date: 2019-09-02
Concrete pouring at #4 Section of Baihetan Dam’s auxiliary weir reached the dam crest on August 23 as the pouring work for the whole weir is on completion in coming October.
Located 360m down to the dam, the auxiliary weir of the Baihetan Dam is a concrete gravity dam. Together with the plunge pool, it constitutes the flood discharge and energy dissipation facility of the dam, which can withstand a discharge flow of up to 30,000 m3 per second with a maximum flood discharge power of 60,000 MW.
The elevation of the auxiliary weir is 608m with a maximum dam height of 67m, maximum width of 67m at the foundation, and a length of 173m at the crest. The project consists of 9 dam sections with a total concrete pouring volume of 280,000 m3. The whole dam is cast with low-heat cement concrete.