Baihetan hydropower plant hoists the last 1 GW generator seat ring into the nest

Date: 2019-11-11

5

Baihetan hydropower plant hoists the last 1 GW generator seat ring into the nest on the left bank on November 3.

The first seat ring was shipped to the site and began assembly on September 15, 2018. It was hoisted into the nest on November 24, 2018. The last seat ring started assembly on September 6, 2019 and welding on September 11.

A total of 8 seat rings for the left bank completed assembly and welding within 16 months, laying a solid ground to make it an excellent mechanical and electric project.

All Copyrigh

By China Three Gorges Corporation

Reprinting or mirroring is strictly prohibited without written authorization,

and offenders will be held liable.

Baihetan hydropower plant hoists the last 1 GW generator seat ring into the nest

Date: 2019-11-11

5

Baihetan hydropower plant hoists the last 1 GW generator seat ring into the nest on the left bank on November 3.

The first seat ring was shipped to the site and began assembly on September 15, 2018. It was hoisted into the nest on November 24, 2018. The last seat ring started assembly on September 6, 2019 and welding on September 11.

A total of 8 seat rings for the left bank completed assembly and welding within 16 months, laying a solid ground to make it an excellent mechanical and electric project.

All Copyrigh

By China Three Gorges Corporation

Reprinting or mirroring is strictly prohibited without written authorization,

and offenders will be held liable.

Contact Us
Address :No. 1 Liuhe Road, Jiang'an District, Wuhan City, Hubei Province, China

Site Map

Link

Copyright 2022-2026 - China Three Gorges Corporation. All rights reserved.
Copyright 2022-2026 - China Three Gorges Corporation.