The ninth unit of the Baihetan HPP has put into operation

Date: 2022-06-08

16459124289900515613(1)

Unit 6 of the Baihetan Hydropower Station successfully passed the 72-hour trial operation and was officially put into operation on June 2. This is CTG’s 103rd hydro generator unit that has been put into operation on the Yangtze River mainstream.


The project had generated over 27 billion kWh of clean electricity. After full completion, it will be the world's second biggest power station after the 22.5 GW Three Gorges Project, with a multi-year average power generation capacity of 62.443 billion kW, and will continuously boost the world's largest clean energy corridor.

All Copyrigh

By China Three Gorges Corporation

Reprinting or mirroring is strictly prohibited without written authorization,

and offenders will be held liable.

The ninth unit of the Baihetan HPP has put into operation

Date: 2022-06-08

16459124289900515613(1)

Unit 6 of the Baihetan Hydropower Station successfully passed the 72-hour trial operation and was officially put into operation on June 2. This is CTG’s 103rd hydro generator unit that has been put into operation on the Yangtze River mainstream.


The project had generated over 27 billion kWh of clean electricity. After full completion, it will be the world's second biggest power station after the 22.5 GW Three Gorges Project, with a multi-year average power generation capacity of 62.443 billion kW, and will continuously boost the world's largest clean energy corridor.

All Copyrigh

By China Three Gorges Corporation

Reprinting or mirroring is strictly prohibited without written authorization,

and offenders will be held liable.

Contact Us
Address :No. 1 Liuhe Road, Jiang'an District, Wuhan City, Hubei Province, China

Site Map

Link

Copyright 2022-2026 - China Three Gorges Corporation. All rights reserved.
Copyright 2022-2026 - China Three Gorges Corporation.