Seat ring volute of 1st unit of Zhejiang Tiantai Pumped Storage Power Station in place

Date: 2024-06-04

060402

The seat ring volute of the first unit of the Zhejiang Tiantai Pumped Storage Power Station in Tiantai county, east China's Zhejiang Province, was recently hoisted in place.

This achievement was facilitated by an innovative workshop technique that involved pre-assembling the seat ring, volute, and extension section through welding. It marked the first time such an innovative approach has been developed and successfully applied in the Chinese pumped storage industry, cutting at least 10 days from the construction schedule.

The total installed capacity of Tiantai Pumped Storage Power Station stands at 1.7 million kilowatts, featuring a rated head of 724 meters.

Upon completion, it will play a key role in the Zhejiang power grid, helping with such tasks as peak load regulation, valley filling, frequency regulation, phase modulation, power storage and emergency support.

All Copyrigh

By China Three Gorges Corporation

Reprinting or mirroring is strictly prohibited without written authorization,

and offenders will be held liable.

Seat ring volute of 1st unit of Zhejiang Tiantai Pumped Storage Power Station in place

Date: 2024-06-04

060402

The seat ring volute of the first unit of the Zhejiang Tiantai Pumped Storage Power Station in Tiantai county, east China's Zhejiang Province, was recently hoisted in place.

This achievement was facilitated by an innovative workshop technique that involved pre-assembling the seat ring, volute, and extension section through welding. It marked the first time such an innovative approach has been developed and successfully applied in the Chinese pumped storage industry, cutting at least 10 days from the construction schedule.

The total installed capacity of Tiantai Pumped Storage Power Station stands at 1.7 million kilowatts, featuring a rated head of 724 meters.

Upon completion, it will play a key role in the Zhejiang power grid, helping with such tasks as peak load regulation, valley filling, frequency regulation, phase modulation, power storage and emergency support.

All Copyrigh

By China Three Gorges Corporation

Reprinting or mirroring is strictly prohibited without written authorization,

and offenders will be held liable.

Contact Us
Address :No. 1 Liuhe Road, Jiang'an District, Wuhan City, Hubei Province, China

Site Map

Link

Copyright 2022-2026 - China Three Gorges Corporation. All rights reserved.
Copyright 2022-2026 - China Three Gorges Corporation.