Reverse power transmission test completed for booster station, associated outgoing project at CTG Brasil's Arinos photovoltaic project
Date: 2024-06-10
CTG Brasil's Arinos photovoltaic project recently completed the reverse power transmission test of its self-built booster station and associated outgoing project, preparing it ready for grid connection.
The project, initiated in July 2022, involves a 500 kV booster station, outgoing transmission lines and the connection interval at Arinos Switch Station No. 2. The booster station and connection interval's successful connection to the power grid will effectively enhance the stability and reliability of the Arinos solar complex's outgoing system, ensuring continuous clean energy transmission.